Naylor Jennings Dyeworks

Client: Yelcon Homes  |   Project Location: Rawdon, Leeds  |   Project Duration: 12 Months

 
 

We carried out a full demolition of the former dye works in Rawdon, Leeds, the site was 7 acres in total. All concrete slabs and foundations were removed and crushed onsite for reuse, a total of 15,000 tonnes were processed for reuse. 2000 tonnes of walling stone was recovered from the site for reuse. Our team removed Notifiable and Non Notifiable asbestos. 

There was a full refurbishment work and soft tip to the mills that were listed. The demolition was carried out in various stages on a listed mill that was structurally unsafe for rebuild.

28548467_10157516586692588_769399659_o.jpg

The image below displays a before and after aerial view of the site:

03a01d8d-71d7-40cb-9eec-6e96a192e90b.jpeg